Project Overview

The City of Milwaukee - Department of Public Works (DPW) is reconstructing W. Keefe Avenue from N. 18th Street to N. 8th Street. Construction is planned to begin in Spring 2027.

Prior to reconstruction taking place, lead service lines replacements will take place on the street, as well as a sewer relay.

The purpose of this project is to improve utilities, improve safety, and address pavement deficiencies. The proposed reconstruction on W. Keefe Avenue will maintain the current street width while including curb extensions and raised crosswalks at various intersections to improve safety for all users.

During the street reconstruction, W. Keefe Avenue will be fully closed to traffic and cross traffic will be maintained at intersections, where feasible. No signed detour route will be provided.